Disaster recovery planning (DRP)

Recovery strategies, hot/warm/cold sites, failover and testing a DR plan.

Key points

  • A DRP describes how IT systems and data are restored after a major outage.
  • Alternate sites trade cost against speed: a hot site is fully equipped and current, so failover is fastest and most expensive; a warm site has hardware but needs data restored, so it is slower and cheaper; a cold site offers only space and power, so it is slowest and cheapest.
  • A DRP is only trustworthy if it is tested regularly.

Practice questions

Single choice

Which alternate site offers the fastest recovery but at the highest cost?

  1. Hot site
  2. Warm site
  3. Cold site
  4. Home office
Show answer

Answer: A. Hot site

A hot site mirrors production and is ready almost immediately. Warm and cold sites need progressively more time to become usable.

Select all that apply

Which are valid ways to test a disaster recovery plan?

  1. A tabletop walkthrough with the recovery team
  2. A scheduled failover to the alternate site
  3. Filing the plan and never opening it
  4. Waiting for a real disaster to find out
  5. Reading it once at approval time
Show answer

Answer: A. A tabletop walkthrough with the recovery team, B. A scheduled failover to the alternate site

Walkthroughs and simulated failovers exercise the plan safely. Never testing, or only reading it once, leaves the plan unproven.

True or false

True or false: having backups means the disaster recovery plan has been proven to work.

Show answer

Answer: False

False. Backups are one ingredient; only a restore or failover test shows the plan meets its recovery targets.

Practice 8 questions on this topic in Bitzu

Short lessons, instant explanations and spaced review of what you get wrong. Free on iOS and Android.

Download on the App StoreGet it on Google Play

More CC topics in this module